WEEKLY HIGHLIGHTS FOR WEEK ENDING 08 January 1999:
STANFORD HIGHLIGHT
The first telescope detector package assembly has been assembled and now
is
in test. This is the first of the two detector package assemblies
required
for flight. The second of the two detector package assemblies
is partially
built and will be tested immediately following the completion
of testing of
the first package. Photo1: Telescope Electronics, Photo 2:
Detector Package Assembly
SPACE VEHICLE HIGHLIGHT
Both flight Telescope Readout Electronics (TRE) boxes successfully passed
their first box-level complete ambient functional tests and voltage
stability tests as part of the TRE Acceptance Test sequence. Photo:
LMMS engineer Bob Farley and Quality Engineer Mike Sisley performing
TRE
acceptance testing.