WEEKLY HIGHLIGHTS FOR WEEK ENDING 16 NOVEMBER 2001:
SIM 3 SUCCESSFULLY COMPLETED
MOC SIM 3 was successfully completed. This sim was the first full scale, multi-day simulation of the mission timeline. A team of more than 50
persons participated in this task. The simulation ran very smoothly. A number of minor anomalies were found during operations. The team handled
these anomalies as true mission events/issues and resolved them in real time. Mission planning, data processing, and orbit determination functions
were all used as they will be during the actual mission. The processes of planning (meetings), control (signoff of templates), and other procedural
issues were exercised by this simulation.
Photo: The Mission Operations Center and crew during the simulation.
FORWARD EQUIPMENT ENCLOSURE TOP PANEL SUCCESSFULLY INSTALLED
The Gravity Probe B team succesfully installed the Forward Equipment Enclosure Top Assembly Panel (FEETAP) on to the Gravity Probe B Space
Vehicle in LM B/205.
Photo: LM team in front of the GP-B Space Vehicle with installed FEETAP in LM B/205. Pictured are: (on scaffolding) Ray Howard and Dale Stephens, (standing) Tom Welsh, Otis Jones, Berto Rodriguez, and Neil Geiger. Not pictured: Bud Swihart.