WEEKLY HIGHLIGHTS FOR WEEK ENDING 28 AUGUST 1998:

STANFORD HIGHLIGHT
Bob Farley has completed testing the printed wire assemblies for the Telescope Readout Electronics (TRE) flight units. Test results were excellent and met all requirements except for minor faults, which will be fixed with minimal rework. Photo: Telescope Electronics

SPACE VEHICLE HIGHLIGHT
A successful Standard Power Regulation Unit (SPRU) Final Data Review was held on Aug 24 at Engineered Magnetics, Rancho Dominguez, CA. In addition to LMMS Engineering and Quality Assurance, DCMC representatives also attended. Data from all functional testing was evaluated and trended to ensure consistent performance throughout the test program. All data anomalies were resolved, enabling the unit to be formally bought off. Photo: LMMS Quality Assurance Representative Rusty Gray and engineer Shawky Shehata inspecting the SPRU after a solder rework