WEEKLY HIGHLIGHTS FOR WEEK ENDING 24 MAY 2002:

TWO FUNCTIONAL PAYLOAD BOX SPCS RUN ON SPACE VEHICLE
The first functional test dry runs for the SRE and GSS boxes were completed on the space vehicle. Both tests were successful. The plan is to update the SPCs and rerun each in the near future. The telescope end-to-end light test (15.35) was successfully run. This test demonstrated the ability of the flight telescope electronics to detect light incident on the science telescope using a GSE light source. The vatterfly test (15.32) was run on the space vehicle. A test anomaly was found and is in-work. The anomaly will likely have no effect on service.

Photo: The GSS hardware

HELD GSS ADR AND TECHNICAL SUMMIT
The GSS box acceptance data review was successfully held. The associated action items are in work. MSFC, Lockheed Martin, and Stanford University held a technical summit. The purpose of the meeting was to work open issues and open verifications. Closure plans were developed for these items.

<<Previous Highlight    Next Highlight>>


Index of Highlights