WEEKLY HIGHLIGHTS FOR WEEK ENDING 5 MAY 2000:
PAYLOAD HIGHLIGHT
The Lockheed Martin probe rework team has completed the rework operations on 3 of the 4 probe HEX (Heat EXchanger) locations.
Small Photo: A member of the rework team working on the neck tube of the probe.
Large Photo (click to view): Insertion of thermocouples into the probe to test the Heat Exchangers.
SPACE VEHICLE HIGHLIGHT
The Forward Equipment Enclosure Top Assembly Panel (FEETAP) was delivered to
LMSS B/205 from Composite Optics, Inc. on April 27, 2000.
Photo: LMSS Engineer Shawn Shelton with the FEETAP in its shipping container at LMSS B/205.