WEEKLY HIGHLIGHTS FOR WEEK ENDING 6 AUGUST 1999:

STANFORD HIGHLIGHT

The UV lamp acceptance review was held in Toronto, Canada. Sasha Buchman, Bruce Clarke, and Dorrene Ross attended the meeting. The 2 primary lamps passed all functional and performance testing with vibration testing still to complete. In addition, the proton monitor has passed the manufacturer's performance and environmental testing. The unit is ready for shipment to Stanford for final testing and acceptance.

Small Photo: a profile of the UV Lamps
Large Photo (Click small photo to view): The team attending and performing the inspection.

SPACE VEHICLE HIGHLIGHT
The Integrated Test Facility is fully operational in its new location in B/205.
Photo: LMMS engineer Gary Rubio in the new ITF clean room in B/205.

<<Previous Highlight   Next Highlight>>

Index of Highlights