WEEKLY HIGHLIGHTS FOR WEEK ENDING 14 MARCH 2003:
SUCCESSFULLY COMPLETED SPACE VEHICLE SPIN BALANCE
The space vehicle test team has successfully completed critical NASA milestone 36 Space Vehicle Spin Balance Complete. The PDU
has been installed on the space vehicle with power up scheduled to take place within the next few days. The ACE has successfully completed
acceptance test. The Spectrum Astro team is reducing the data in preparation for the upcoming acceptance review.
Photo: The GP-B spacecraft outside the thermal vacuum chamber (taken from inside the chamber).